  • Lahore Smart City: Sector A Development Update

    Here is a behind-the-scenes look at the on-ground progress at https://lahorerealestate.net, where infrastructure work continues to shift across several blocks and sectors.

    A detailed ground assessment offers a clear view of the current development status for Overseas West Sector A, with attention to street-by-street progress, utility preparation, and paving work.

    On Street Number 1, earthwork and soil filling have been completed along the road corridor. The watering and ground preparation phase is fully done, and this prepares the surface for the next phases. Tuff tile installation is set to begin on the prepared surface. On one side of the street, utility poles have been put up, but the street light fixtures are still waiting. On the other side, pedestrian footpath work is still pending, and more poles and fixtures are planned for later phases.

    On Street Number 2, major paving progress has taken place. About 80 percent of the developed segment had its tuff tiles laid. On an unfinished patch, materials were delivered, earth was spread, and the final watering and compaction are still needed before tile laying can start. Where paving is done, both street light poles and working light fixtures are installed, and pedestrian walkways on both sides are mostly paved. Still, the street is not fully finished. Only about half of the corridor up to specific mapped plots is paved, and the further stretch has no active development right now.

    Lane Number 16 runs behind plots facing the Ring Road in Sector A. Sand and sub-base material have been laid, and watering and compaction are nearly finished. Footpath paving is underway, with crews handling tile delivery and installation. Beyond Street Number 3 along Lane 16, road surface tuff tiles have been laid over most of the section, leaving minor edge detailing and final finishing before completion.

    On Street Number 3, advanced paving is visible. Nearly 90 percent of the road surface has installed tuff tiles. Work continues on a small remaining segment to close the gap and connect with adjacent pathways. Labor teams are placing pavers by hand on the compacted base, and this section is close to structural completion.

    On Street Number 4, the footpath framework on both sides is almost complete, with small gaps left for final tiling. Pavers are stacked nearby to finish those footpath sections. The paved road part has completed tuff tiles on both sides. Still, like Street Number 2, only about 40 to 45 percent of the total street alignment is developed, so plots farther down are untouched by road infrastructure. Street lighting poles have not been placed yet.

    Street Number 5 has a nearly identical development profile to Street Number 4. The main road surface in the developed section is paved, and its tie-in with Lane Number 16 requires only final edge alignment. Part of the pedestrian footpath still needs finishing, and light poles have not been erected. Progress on Street 5 remains confined to roughly 40 to 45 percent of its mapped length, with no current construction activity visible on the remaining section.

    The work then shifts from paving to foundational earthworks. On Street Number 6, initial ground leveling was done. Concrete kerb stones mark the footpath boundaries on both sides and set the structural corridor. Tuff tile installation for the carriageway and walkways has not begun yet, and work waits for surfacing machinery and paving teams to move forward from earlier streets.

    On Street Number 7, heavy earthmoving equipment finished basic ground leveling. Curbs are aligned on one side of the street to outline the walkway, while the other side awaits curbing. Underground sewerage installation is partly incomplete along this corridor. Full-scale surface development and tile paving on Street Number 7 will follow completion of the foundational utilities.

    On Street Number 8, the road runs beside an adjacent designated neighborhood park area. Basic leveling across the road alignment is complete, and curb stones define the perimeter of the adjacent green space. Footpath completion and road paving are still pending. Street Number 9 is at the same stage: the surface is leveled, a curved curb line borders the open park quadrant, but roadway surfacing, opposite-side footpaths, and electrical pole installations are yet to happen.

    On Street Number 10, deep utility work is the focus. About 80 to 90 percent of the underground sewerage network is installed, but road leveling, curbing, and surfacing remain on hold pending final utility sign-off.

    Street Number 11 currently has raw earth mounds and early excavation areas where digging began before. No resurfacing, leveling, or structural paving has advanced there recently. Beyond Street Number 11, toward outer perimeter plots and areas facing the Ring Road next to the executive sector, the ground stays undeveloped and raw, matching earlier survey periods.